Projects on schedule2 of 31 behind
Workers today568 of 62591% of scope
Reports in today46 of 515 missing
Short-staffed today2 contractors8 short
Sentosa Prime
2 days aheadTowers A and B · PM Rajesh Kumar
94%
overall progress
▲ 2 days ahead of plan· plan 91% today
PlanWorkers284 of 305
Reports18 of 21
Problems3 open
Open project dashboardSentosa Edge
5 days behindTowers A and B · PM Rajesh Kumar
50%
overall progress
▼ 5 days behind plan· plan 62% today
PlanWorkers198 of 240
Reports14 of 21
Problems5 open
Open project dashboardSentosa Era
On scheduleTowers A, B and C · PM Rajesh Kumar
24%
overall progress
● On plan· plan 24% today
PlanWorkers86 of 80
Reports6 of 6
Problems1 open
Open project dashboardWaiting for your decision
Sentosa EraSchedule submitted for approvalEra · Tower B · 96 activities · Rajesh Kumar, 11:20 AMReview schedule
Sentosa EdgeDate change requestedEdge · Tower A, 16F · moved to 2 Sep · Rajesh KumarReview request
Sentosa EdgeProblem escalated to youEdge · Tower A, 14F · material short · Suresh PatilOpen problem
View allShort-staffed today
Sentosa EraBala Painters · PaintingEra · Tower B · 2 of 10 recorded · flagged 9:12 AM10 short
Sentosa EdgeShree Tiling Works · TilingEdge · Tower A · 4 of 14 recorded · flagged 9:30 AM5 short
Sentosa EdgeDev Drill Works · TilingEdge · Tower B · 3 of 8 recorded · flagged 9:45 AM5 short
View allReports still missing
Sentosa Edge - Phase 1Tower A · Suresh Patil · due by 7:00 PMView Sentosa Era - Phase 1Tower B · Mahesh Rane · due by 7:00 PMView View allRecent activity
Rajesh Kumar approved Blockwork, 12th floor4:12 PMSentosa Edge · Tower B
Suresh Patil submitted the Tower A daily report3:40 PMSentosa Edge · 3 photographs
Mahesh Rane added Mane Scaffolding Works on site2:05 PMSentosa Era · 6 workers
Deepak Joshi sent back Slab reinforcement11:20 AMSentosa Edge · Tower A, 14F
View all